Dust Collector in Acoustic Shed
ClientCross Yarra Partnership

John Holland Pty Ltd

Lendlease Engineering Pty Ltd

Bouygues Construction Pty Ltd

LocationMelbourne, Victoria, Australia
ApplicationVentilation and Dust Control for Tunnel Construction
Supply SummaryFull Extract Ventilation Design
Design, Manufacture & Supply:
– 9 x JMS-60-MES
– 1 x JMS-40-MES
– 2 x JMS-10-MEC-XP
– 3 x JMS-10-MES
– 3 x JMS-30-MDT

Project Overview

The Metro Tunnel is a key rail infrastructure project currently under construction in Melbourne, Australia that includes the construction of twin 9km rail tunnels between South Kensington station and South Yarra with five new underground stations. While TBMs are being used to build most of the Metro Tunnel, station box excavation and tunnelling between the two CBD stations is being undertaken by roadheaders.

Site geology comprises of interbedded Siltsone and Sandstone known as Melbourne Formation. The mineralogy in its unweathered state typically comprises a mineral assemblage principally of quartz (35% up to 59%). The dust produced when mining these minerals can be hazardous to the health and safety of workers if inhaled.

Our Solution

The Cross Yarra Partnership, a consortium comprising of, John Holland Pty Ltd, Lendlease Engineering Pty Ltd and Bouygues Construction Pty Ltd, initially contracted Grydale to provide a ventilation design system for the construction of the Metro Tunnel. Grydale was later contracted to supply all dust collection equipment required for the duration of construction works.

Initial engineering consultation converted the ventilation design from an Overlap or Cross-Over Extraction methodology to the now in-situ, proven Extract methodology. Within full extract ventilation systems, air is drawn through the tunnel using negative pressure from the outside and is exhausted via ducting to a dust collector to deliver clean air to the atmosphere. This system removes all contaminants from the tunnel at the face and supplies fresh clean air for Civil, Mechanical and Engineering Works.

The Metro Tunnel provided some unique challenges for the ventilation design, including space and noise constraints plus the location on excavation works within the CBD.

The design was created using Ventsim Design 5 to simulate ventilation, airflows, pressures, heat, gases,
radon, fire and other key ventilation data to be considered, along with managing the financial constraints of the project.

The ventilation design was separated into 13 stages, representing the tunnel area changes, and was designed around the last dig sequence, where maximum air flow is required. The ventilation design utilises dust collectors for each stage, with additional axial fans to boost airflow in the latter stages of construction.

Melbourne Metro Tunnel Project
Trinocular cavern construction methodology
Trinocular Caverns

The Melbourne Metro Stations will be built as trinocular caverns, where three overlapping tunnels will be mined by roadheaders to create a platform width that will be around 19m – one of the widest metro platforms in the world.

Two temporary acoustic sheds up to 20m high enclose construction sites within the CBD to minimise the impact on residents, businesses and the local community, from the construction of the stations. A system of louvres on the outside of the acoustic sheds help to control clean air flow into the tunnel. The ventilation system was also designed for environmental noise limits while balancing required air flow into the tunnel.

Since construction began, Grydale has designed, manufactured and supplied the following dust collection systems, in line with the ventilation design:

CBD North – 4 x JMS-60-MES (60m3s, mobile, electric, drag skid units).
CBD South – 5 x JMS-60-MES (60m3/s, mobile, electric, drag skid units). CBD South had further space constraints, so these units were customised to have four roof-mounted fans to provide a reduced footprint so dust collectors can be located within the acoustic shed.
Parkville – 1 x JMS-30-MDT (30m3/s, mobile, diesel, track unit) and 3 x JMS-10-MES (10m3/s, mobile, electric, drag skid unit) were rented to provide short-term dust extraction at source.
Tunnel Cross Passages – 2 x JMS-10-MEC-XP (10m³/s, mobile, electric, castor wheel units). These units were designed for the tight space constraints of tunnel cross passages. The castor wheels allow units to slide onto the platforms in the cross passages for the duration of construction.
Rental Units – 3 x JMS-30-MDT (30m³/s, mobile, diesel, track units) have been utilised for dust extraction within backend works at various project work sites.

20m High Temporary Acoustic Sheds

The JMS-60-MES dust collection units run 415kW fan motors with Variable Speed Drives (VSD) which has allowed up to 40% in power savings. The excavation sequence has been programmed into the dust collectors via the Programmable Logic Computer (PLC) so as excavation advances, power progressively increases.

The ventilation design for the CBD underground stations utilises a mix of negative and positive pressure systems while design for Parkville and Anzac stations and the portals, use positive pressure ventilation. The latter back-end works are supported with mobile source extraction units for shotcrete and other works where dust or fibre controls extract dust at source, in addition to the supplied air ventilation.

In each acoustic shed, twin JMS-60-MES large volume dust collection units move up to 120m³/s (>250,000
CFM) via 350m of underground duct. Each unit features 84 high efficiency filter cartridges that are cleaned by reverse pulse using the onboard air compressor. Product is discharged via a hydraulic reversable auger and collected into bulker bags.

More Information? Contact Us.

If you would like more information please complete the form below.

We try to respond to requests on the same business day, however if your enquiry is urgent please call our team on +1 888 479 3253. Our office hours are between 07:00 and 17:00 Monday to Friday.